SNCC Projects Advisor | Core Work for October 2026

Monthly report & update to community of Strathnairn

SNCC Projects Advisor | Core Work for October 2026

 

Carn Na Saobhaidh Wind Farm 

COMMUNITY ENGAGEMENT

Engagement on, liaison with and support of the local community, over the month; intended both to support a return of community feedback to the developers ahead of a forthcoming planning application, and fed into this process, and also to understand the greatest areas of concern. This followed an awareness raising campaign and sign-posting to the amended development proposal.

Information fed to the community through a range of media, plus held a series of local Community Cafe Surgeries – with SNCC’s Beth Rose – to discuss the project, hear and document local concerns.

 

ON HYDROLOGY & FLOOD RISK

Liaison with RES as Developer over Hydrology & Flood Risk to Achvraid, Croachy, Brin etc. This was undertaken through direct correspondence (with SNCC and HC copied in) plus telehone meetings. Community concerned that fragile landscape, existing geology and the upland holding capacity is not aggravated through proposed investigative or development works. Seeking assurances that any planning consent/development works will not give rise to flooding – in what is already a populated but fragile community – or affect the natural water course (and water supply), to the detriment of the local community. Instead seeking to make consent conditional to restoring peatlands, and nature restoration works, to increase the holding capacity at higher grounds, ahead of or during construction, and not post development works.

Reason: To understand the impact of and reduce flood risk, in the interest of the local community.

 

ACOUSTIC & VISUAL IMPACT ASSESSMENT

Made a preliminary assessment of the proximity of turbines to the community, and the likely effect of overshadowing, shadow flicker, airbourne and impact sounds through mapping, feasibility studies (scoping documents), plus drawing on local knowledge and lived experience. Particularly concerned about potential impacts at certain times of year (with low sun) or in particular weather conditions (owing to existing landforms of the area and known echo). To future-proof the community these matters have been discussed in full with SNCC plus recommend actioning a range of measures to record pre-construction data, in these key areas.

Reason: For the purpose of having accurate local records and establishing the base line data ahead of any changes pre-construction in the interest of local community, in the event these are required later.

 

Strathnairn Dark Skies & Planning System

 

SECURING NATIONAL/WIDER SUPPORT

Attended Science in the Atrium at Inverness Royal Academy, and secured an advance meeting with Professor Catherine Heymans, Scotland’s Astronomer Royal. This was to introduce Professor Heymans to our local works, seek her support for Strathnairn Dark Skies, and back the community over the current Dark Skies International Application.

 

COMMUNITY ENGAGEMENT

Raised awareness through a range of mediums – over the month –  Highland Council’s Draft Policy supporting the regions’ Dark Skies.  Contacted all the external supporters and partnering organisations to increase engagement and support of the same.

Liaised on and set-up November Event; with SSG Chair, Andy McGregor.

 

FEEDBACK INTO PROCESS

Supported the community to inform this process; and fed back at a community level.

Reason: To protect Dark Skies, in the interest of the local community.

 

General Support

  • Attendance of SNCC Monthly Meeting, for support on large scale infrastructure works and related planning matters (Aberarder WF & Grid Connection, Carn Na Saodhaidh WF, HC Dark Skies)
  • Support for increased community engagement on SSEN Aberarder Fund & awareness raising of the importance of Community Participation on the Local Funding Forum; in highlighting the significance of this to local community.
  • Website & IT support