Aberarder Wind Farm Connection Project_Current Stone Deliveries

SSEN Aberarder Wind Farm Connection Project

***Current Stone Deliveries / SSEN & A Mackenzie Haulage of Newtonmore***

Community Update from Kirsty McNamara, Community Liaison Manager, SSEN Transmission (at time of writing, and following SNCC Liaison Oct 26) >

Following discussions at the recent Community Council meeting, we are writing to provide further information on upcoming works over the next few months associated with the Aberarder Wind Farm Connection Project and to provide additional detail on the points discussed.

Material Deliveries
Following our discussions at the Community Council meeting, we now have confirmation of when stone deliveries which are expected to start next week (at time of writing) and continue until the end of January 2027.

These deliveries are required to support the construction of access track works, with stone being transported from Daviot Quarry for construction of the access tracks
up at the Aberarder site.

Current estimate movements include:
• Around 10 stone deliveries per working day
• Deliveries using 32-tonne tipper HGVs
• Approximately 20 tonnes of stone per load
• Delivery of Plant Machinery to conduct the access track works which will only
take place once, and then for removal once works are completed.

Delivery numbers may vary per week depending on construction progress, site requirements and weather conditions. The deliveries are taking being carried out by A.Mackenzie Haulage. I’ve attached photos of the vehicles used below, so they are identifiable on the road.

Community Council Meeting Follow-Up

School Timings
We appreciated the concerns raised by the community council about school timings.

Deliveries will be scheduled to avoid peak school pick-up and drop-off times, between 8:15–9am and 3–3:45pm, Monday to Friday. On Fridays, deliveries will also avoid 12:15–12:45pm to account for Farr Primary School’s earlier finish time.

Traffic Management Plan
Our Construction Traffic Management plan has undergone revisions due to some amendments made and is currently being signed off internally. We will share this as soon as possible.

Helicopter Use and Movements
Since it was raised at the Community Council meeting, we have now begun the process of creating a flyer which will include information about the use of helicopters for the project and the benefits this brings to the community and the business as a result. We will ensure the helicopter movements are communicated to the relevant landowners and the community prior to starting this element of works.

Concerns, Opportunities and Feedback
We welcome ongoing feedback from the Community Council and the wider community as the project progresses. If you have any concerns, suggestions or opportunities you would like to discuss, please contact me directly. This helps ensure that any matters raised can be shared with the appropriate project team members and escalated where necessary, so they can be addressed and responded to appropriately.

We will be liaising with SSE Renewables about the future Community Liaison Group meeting to provide a further update then as well.

Kind regards,
Kirsty McNamara
Community Liaison Manager
SSEN Transmission

 

More details > 

For full details on Aberarder Wind Farm Connection Project Aberarder Wind Farm Connection – SSEN Transmission