A9 Tomatin/Moy – Realignment of the A9 at Lynebeg & new junction

A9 Tomatin/Moy – Realignment of the A9 at Lynebeg & new junction

From 15 August, both lanes of the A9 will be temporarily realigned at Lynebeg. This is required to allow for the construction of a new underpass at Lynebeg, and the realignment will remain in place until the completion of this underpass in approximately Autumn 2027....

UPDATE ON LYNEMORE WIND FARM, LIVE PLANNING APPLICATION & ECU

UPDATE ON LYNEMORE WIND FARM, LIVE PLANNING APPLICATION & ECU

COMMUNITY UPDATE Lynemore Wind Farm  ECU 00005105 WHAT'S THE STATUS OF THE PROJECT? Galileo Empower UK's Lynemore Wind Farm is currently being considered as a live planning application; registered as ECU 00005105. The proposal is for 14 turbines @ 200m to tip of...

Temporary Roundabout A9  Tomatin and Moy From 6 May for 3 weeks

Temporary Roundabout A9 Tomatin and Moy From 6 May for 3 weeks

Notification of temporary 24 hr traffic signals on the A9 between Tomatin and Moy and temporary realignment of the A9 at Dalmagarry. As part of our ongoing commitment to engage with the local community, we are writing to advise you of upcoming traffic management being...

A9 dualling – traffic management update

A9 dualling – traffic management update

Notification of installation of major temporary traffic management on the A9 between Tomatin and Moy for A9 Dualling As part of our ongoing commitment to engage with the local community, we are writing to advise you of plans to implement major traffic management on...